Navigate through the complexities of ancillary construction documents with our practical guidance. Essential for ensuring smooth project execution and compliance, this resource addresses overlooked yet crucial agreements and forms, bolstering your expertise in managing all facets of construction projects. Unlock insights into frequently utilised but often misunderstood supplementary construction documents, enhancing your ability to mitigate risk and streamline project management. Equip yourself with the knowledge to draft, review, and negotiate these vital documents effectively.
Supreme Court confirms that contractor must have accrued right to terminate under clause 8.9.4 of the JCT Design and Build Contract 2016 (Providence Building Services v Hexagon Housing Association)
The following Construction news provides comprehensive and up to date legal information on Construction weekly highlights—15 January 2026
What are preliminaries in a construction contract?What are prelims?‘Preliminaries’ in a construction contract, or ‘prelims’, is typically taken to...
What is a variation on a construction project?A variation (sometimes referred to as a change) is an alteration to the scope of work originally...
Time of the essence—construction contractsWhat does time of the essence mean?Where time is 'of the essence' it means that the stated time for...
Product liability insurance for the construction industryThis Practice Note looks at product liability insurance from the perspective of those engaged...
Letters of intent—constructionWhat is a letter of intent?Letters of intent are used in construction and engineering projects to allow the employer to mobilise a contractor before the employer is in a position to enter into the full building contact. The letter may only instruct the contractor to
Advance payment bondsAn advance payment bond is a particular form of performance bond, invariably written as an 'on demand' instrument. See Practice Notes: Performance bonds—construction projects and On demand performance bonds—construction projects.This Practice Note examines:•the nature of advance
Strike out—making an application to strike out a statement of caseA strike out order can be made either following an application by the parties or on the court's own initiative. This Practice Note deals with the scenario of the order being made following a party's application.Making an application
Contributory negligence in personal injury claimsContributory negligence is a partial defence which can lead to a discount in damages.Other defences may also be relevant. See Practice Notes: Did the claimant consent to the risk of injury? and Was the claimant involved in an illegal activity?If a
0330 161 1234