Standard form construction contracts

Featured guidance
Standard form construction contracts guidance:

Produced in partnership with CMS This document contains suggested amendments and additional clauses to be incorporated into our schedule of amendments to the JCT Design...

Precedents

Produced in partnership with CMS This document contains suggested amendments and additional clauses to be incorporated into the Construction schedule of amendments to the...

Precedents

This document contains quick links to searchable PDF copies of the Chartered Institute of Building (CIOB) Time and Cost Management Contract 2015 suite of contracts. See...

Practice Note

The ‘CIOB Contract for use with Complex Projects, First Edition 2013’—CPC 2013 for short—was published by the Chartered Institute of Building (CIOB) in April 2013 and was...

Practice Note

Development of the rules CIMAR is the acronym for the Construction Industry Model Arbitration Rules, published by the Society of Construction Arbitrators (SCA) and the...

Practice Note

ARCHIVED: This Practice Note has been archived and is not maintained. This article appears as originally published in Construction Law on 1 February 2017 and is not...

Practice Note

ARCHIVED: This Practice Note has been archived and is not maintained. This article appears as originally published in Construction Law on 1 March 2017 and is not...

Practice Note

ARCHIVED: This Practice Note has been archived and is not maintained. This article appears as originally published in Construction Law on 1 April 2017 and is not...

Practice Note

ARCHIVED: This Practice Note has been archived and is not maintained. This article appears as originally published in Construction Law on 1 October 2019. Nick Barrett,...

Practice Note

This Practice Note contrasts and compares key features of the FIDIC 1999 and NEC4 contracts. It focuses on the NEC4 Engineering and Construction Contract (ECC) and the...

Practice Note

This Practice Note contrasts and compares key features of the FIDIC 2017 and NEC4 contracts. It focuses on the NEC4 Engineering and Construction Contract (ECC) and the...

Practice Note

It is vital for contractors to follow the correct procedure for making claims for additional costs and/or extensions of time under the FIDIC contracts. The consequences...

Practice Note

Introduction This Practice Note examines design under the 1999 editions of the Red, Yellow and Silver Books, the Gold Book 2008 and the Pink Book 2010. For a look at...

Practice Note

This Practice Note considers the use of dispute adjudication boards (DABs) in the 1999 editions of the FIDIC Red, Yellow and Silver Books, the Gold Book 2008 and the Pink...

Practice Note

The FIDIC contracts contain a 'multi-tiered' dispute resolution procedure that escalates from adjudication of the dispute by a dispute adjudication board (DAB) to...

Practice Note

This Practice Note considers the procedure to be followed by an employer wishing to make a claim for payment from the contractor or for an extension to the defects...

Practice Note

This Practice Note considers the insurance provisions in the 1999 editions of the FIDIC Red, Yellow and Silver Books. For guidance on the 2017 editions, see Practice...

Practice Note

This Practice Note examines performance and testing under the 1999 editions of the Red, Yellow and Silver Books, the Gold Book 2008 and the Pink Book 2010. For detail on...

Practice Note

This Practice Note examines price under the 1999 editions of the Red, Yellow and Silver Books, the Gold Book 2008 and the Pink Book 2010. For information on price in the...

Practice Note

This Practice Note examines the approach to sub-contracting under the 1999 editions of the FIDIC Red, Yellow and Silver Books, the Gold Book 2008 and the Pink Book 2010....

Practice Note

This Practice Note considers termination by the Contractor under the FIDIC Red, Yellow and Silver Books 1999, the Gold Book 2008 and the Pink Book 2010. It does not...

Practice Note

This Practice Note looks at the Employer’s rights to terminate under the FIDIC Red, Yellow and Silver Books 1999, the Gold Book 2008 and the Pink Book 2010. In relation...

Practice Note

This Practice Note considers the role of the Engineer under the FIDIC Red and Yellow Books 1999 and the Pink Book 2010. The FIDIC Silver Book 1999 and the FIDIC Gold Book...

Practice Note

This Practice Note examines the position under the 1999 editions of the Red, Yellow and Silver Books, the Gold Book 2008 and the Pink Book 2010. In relation to the 2017...

Practice Note

This Practice Note examines variations under the 1999 editions of the Red, Yellow and Silver Books, the Gold Book 2008 and the Pink Book 2010. For detail on variations...

Practice Note

This Practice Note looks at the Conditions of Contract for Plant and Design Build 1999 (commonly referred to as the FIDIC Yellow Book 1999), and the Conditions of...

Practice Note
Trending Topics
In-House COVID-19