Applying statutory requirements when drafting and negotiating construction contracts throws up common problems and disputes. We cover HGCRA 1996 requirements plus other issues lke retention, set off, and escrow.
In-depth guidance and precedent documents for enforcing and challenging the adjudicator’s decision. From correcting errors under the slip rule, to grounds for a jurisdictional challenge, this is the place to go.
We publish JCT 2016 contracts and FIDIC contracts, and have related schedules of amendments for key forms. See other schedules of amendments, practice notes, and checklists for forms including NEC, MF/1, ICC.
Understand the connection between the agreements you’re advising on and what happens on the ground. Know when to push a point or let it go, and give your clients advice they can work with from design to build and beyond.
This week's edition of Construction weekly highlights includes a case in which the Technology and Construction Court (TCC) considered whether an...
The Scottish Government has published a letter to local authorities, outlining changes to the guidance in the Building Standards Technical Handbooks....
Construction analysis: The historic causes of insolvency, the lessons to be learnt from recent case studies and the wider implications for key players...
The Ministry of Housing, Communities and Local Government (MHCLG) has announced a £3bn support package, in the form of government guarantees, aimed at...
The Chair of the National Infrastructure Commission (NIC), Sir John Armitt, has written a letter to the Chief Secretary to the Treasury, the Rt Hon...
Responsible Actors Scheme—eligibility and membershipThe Responsible Actors Scheme (RAS) is a ‘building industry scheme’ for property developers in...
Construction Glossary—XA B C D E F G H I J K L M N O P Q R S T U V W X Y Z X optionsThese are optional clauses in NEC3/NEC4 contracts (known as...
Scaffold licencesPurpose of a scaffold licenceA scaffold licence is normally required where a contractor needs to erect scaffolding for the purposes...
JCT—interpreting the lists of Relevant Events and Relevant MattersThe provisions for Relevant Events and Relevant Matters are central to the...
JCT contracts 2016—what's changed? [Archived]ARCHIVED: This Practice Note has been archived and is not maintained.This Practice Note brings together...
Acceleration AgreementDate [insert date of Agreement]Parties1[insert name of Employer] of [insert address] incorporated in England and Wales with...
Schedule of Amendments to SBCC Standard Building Contract With Approximate Quantities for use in Scotland (SBC/AQ/Scot) 2016The Contract comprises the...
Schedule of Amendments to SBCC Standard Building Contract Without Quantities for use in Scotland (SBC/XQ/Scot) 2016The Contract comprises the...
Schedule of Amendments to SBCC Standard Building Contract With Quantities for use in Scotland (SBC/Q/Scot) 2016The Contract comprises the completed...
Redfern schedule—arbitrationClaimant’s description of documentation requestedClaimant’s position on relevance and materialityRespondent’s response to...
What is a variation on a construction project?A variation (sometimes referred to as a change) is an alteration to the scope of work originally...
Escrow accounts and escrow agreementsThis Practice Note examines why parties involved in a construction project may enter into an escrow agreement (or...
Defects liability period and rectification of defectsIt is common in construction projects for defects to manifest or appear in the works. Most...
What is practical completion?Practical completion marks the end of the construction period of a project, when the works are 'finished' and the...
Build Operate Transfer (BOT) contractsThe Public Private Partnership (PPP) models are a popular way for governments to involve private investment,...
Differences between adjudication and other forms of dispute resolutionThis Practice Note identifies some of the key differences between adjudication...
Liquidated damages in construction contractsThis Practice Note explains what liquidated and ascertained damages (LADs/LDs) are and their purpose in a...
Time at large in construction contractsThis Practice Note examines the concept of ‘time at large’ in relation to the completion of works under a...
Provisional sumsWhat are provisional sums?There is no precise standard definition of provisional sum but it is generally understood to refer to an...
Scott Schedules in construction disputesScott Schedules are often very useful in construction disputes. They help to identify the key issues between...
The final account in construction and engineering contractsWhat is the final account?The expression 'final account' refers to the consolidated...
Fluctuations in construction contractsWhat are fluctuations?Fluctuations provisions are clauses in construction contracts that allow the contract sum...
Breach of natural justice in adjudicationProduced in association with 4 Pump CourtPrinciples of natural justiceIf an adjudicator breaches the rules of...
New home warrantiesThis Practice Note looks at the principal types of policy or guarantee (other than latent defects insurance) that are currently on...
Extensions of time under construction contractsThis Practice Note examines the circumstances in which a construction contract might entitle a...
Buildings insurance provides cover for the cost of rectifying, replacing or reinstating any damage caused to the structure of a property (such as the roof, walls, ceilings, floors, doors and windows) if the damage is caused by an insured risk (as this is defined in the relevant insurance policy).
The liability of a party for defects in their workmanship.
The professional body for chartered surveyors, and a nominating body for adjudicators and arbitrators.