Applying statutory requirements when drafting and negotiating construction contracts throws up common problems and disputes. We cover HGCRA 1996 requirements plus other issues lke retention, set off, and escrow.
In-depth guidance and precedent documents for enforcing and challenging the adjudicator’s decision. From correcting errors under the slip rule, to grounds for a jurisdictional challenge, this is the place to go.
We publish JCT 2016 contracts and FIDIC contracts, and have related schedules of amendments for key forms. See other schedules of amendments, practice notes, and checklists for forms including NEC, MF/1, ICC.
Understand the connection between the agreements you’re advising on and what happens on the ground. Know when to push a point or let it go, and give your clients advice they can work with from design to build and beyond.
The Ministry of Housing, Communities and Local Government (MHCLG) has published updated versions of Approved Document B (fire safety), covering both...
Construction analysis: In this article, we look back on the key developments in construction law that emerged in the later months 2024, and look ahead...
The Ministry of Housing, Communities and Local Government (MHCLG) has published the findings of its first annual survey on local authority planning...
The Welsh Government has published the response to its October 2023 consultation on proposed amendments to Part B (Fire Safety) of the Building...
This week's edition of Construction weekly highlights includes the announcement of closure plans for the Grenfell Tower Inquiry, a case in which the...
Choosing an expertThis Practice Note should be read in conjunction with:•Practice Notes: Expert evidence—general considerations, Applying for...
ADR in the Technology and Construction CourtNote:•this Practice Note gives specific guidance on matters proceeding in the Technology and Construction...
EPC contracts—contractor claimsEPC (engineering, procurement and construction) contracts are frequently drafted to be turnkey agreements—the...
Planning for sustainable development—regulationSustainable development essentially means keeping current development within sustainable levels,...
The National Planning Policy FrameworkVersions of the National Planning Policy Framework (NPPF)The original version of the National Planning Policy...
Schedule of Amendments to JCT Constructing Excellence Contract 2024The Contract comprises the completed Constructing Excellence Contract 2024 Edition...
Interest on late payment clause1Interest on late paymentIf either party fails to make payment in accordance with this Agreement the other party shall...
Precedent s 106 agreementAGREEMENTrelating toSection 106 of the Town And Country Planning Act 1990 [and [insert other legislation]] in relation to the...
Early access licenceDate [date]Parties1[name of Licensor] [of OR incorporated in England and Wales (company registration number [number]) whose...
Licence for alterationsDate [date]Parties1[name of Landlord] [of OR incorporated in England and Wales (company registration number [number]) whose...
What is a variation on a construction project?A variation (sometimes referred to as a change) is an alteration to the scope of work originally...
Escrow accounts and escrow agreementsThis Practice Note examines why parties involved in a construction project may enter into an escrow agreement (or...
Defects liability period and rectification of defectsIt is common in construction projects for defects to manifest or appear in the works. Most...
What is practical completion?Practical completion marks the end of the construction period of a project, when the works are 'finished' and the...
Build Operate Transfer (BOT) contractsThe Public Private Partnership (PPP) models are a popular way for governments to involve private investment,...
Differences between adjudication and other forms of dispute resolutionThis Practice Note identifies some of the key differences between adjudication...
Liquidated damages in construction contractsThis Practice Note explains what liquidated and ascertained damages (LADs/LDs) are and their purpose in a...
Time at large in construction contractsThis Practice Note examines the concept of ‘time at large’ in relation to the completion of works under a...
Provisional sumsWhat are provisional sums?There is no precise standard definition of provisional sum but it is generally understood to refer to an...
Scott Schedules in construction disputesScott Schedules are often very useful in construction disputes. They help to identify the key issues between...
The final account in construction and engineering contractsWhat is the final account?The expression 'final account' refers to the consolidated...
Fluctuations in construction contractsWhat are fluctuations?Fluctuations provisions are clauses in construction contracts that allow the contract sum...
Breach of natural justice in adjudicationProduced in association with 4 Pump CourtPrinciples of natural justiceIf an adjudicator breaches the rules of...
New home warrantiesThis Practice Note looks at the principal types of policy or guarantee (other than latent defects insurance) that are currently on...
Extensions of time under construction contractsThis Practice Note examines the circumstances in which a construction contract might entitle a...
The ‘Building Research Establishment Environmental Assessment Method’ (BREEAM) is a method for evaluating and certifying the environmental performance of a building’s design, construction and operation. A BREEAM score and rating are assigned to BREEAM certified buildings providing a means of measuring the environmental impact of a building’s design and construction and so benchmarking this against other certified buildings.
The document which will prevent the full sums applied for by a contractor being paid over for reasons given therein.
An engineer specialising in the design and installation of building services. Also referred to as an M&E engineer.