Table of contents
- What are the practical implications of this case?
- What was the background?
- What did the court decide?
- Extension of time for Referral Notice
- Interpretation of clause 1.8.2
- Did QFS abandon the adjudication?
- Case details
Article summary
Construction analysis: The Technology and Construction Court (TCC) found that the ‘conclusive evidence’ provisions in a Joint Contracts Tribunal (JCT) form of sub-contract did not apply to an adjudication on the value of the Final Sub-Contract Sum. The court found that the claimant had commenced adjudication proceedings before the Final Payment Notice (FPN) became conclusive evidence of the Final Sub-Contract Sum, meaning that the adjudicator was not bound by it. Further, the claimant’s failure to serve a timely Referral Notice in the adjudication did not mean that the proceedings should have been treated as concluded or abandoned before the adjudicator made his decision.
To continue reading this news article, as well as thousands of others like it, sign in with LexisNexis or register for a free trial