Completion of the works

View Construction by content type:

Latest Construction News

Featured Construction content

Practice notes
This Practice Note identifies some of the key differences between adjudication and litigation, arbitration, mediation and expert...
Read More >
Produced in partnership with 4 Pump Court 12th Jan
Practice notes
What is a target cost contract?A target cost contract is a type of cost reimbursable contract under which the contractor is paid the ‘actual cost’...
Read More >
9th Nov
Practice notes
It is common in construction projects for defects to manifest or appear in the works. Most construction contracts require the contractor to return to...
Read More >
9th Nov
Practice notes
Brexit impact—public procurement: The UK public procurement regime derives from EU public procurement laws, and is therefore impacted by the UK’s...
Read More >
9th Nov
Practice notes
What is a letter of intent?Letters of intent are used in construction and engineering projects to allow the employer to mobilise a contractor before...
Read More >
9th Nov
Practice notes
While tort claims are not as common in construction projects as breach of contract claims, they do still arise and it is not uncommon for a claimant...
Read More >
9th Nov
Practice notes
A variation (sometimes referred to as a change) is an alteration to the scope of work originally specified in the contract, whether by way of an...
Read More >
9th Nov
Practice notes
What is sectional completion?Where the construction contract splits the works into sections or parts, usually to be started at different times, there...
Read More >
9th Nov
Practice notes
This Practice Note explains what liquidated and ascertained damages (LADs/LDs) are and their purpose in a building contract. It considers the...
Read More >
9th Nov
Practice notes
This Practice Note looks at the SBCC (Scottish Building Contract Committee) standard forms of contract and the key differences between them and the...
Read More >
Produced in partnership with MacRoberts LLP 12th Jan
Practice notes
This Practice Note considers ‘pay when paid’ clauses and ‘pay when certified’ clauses in construction contracts, and the relevant provisions of the...
Read More >
Produced in partnership with Womble Bond Dickinson 12th Jan
Practice notes
This Practice Note provides an overview of what interim payments are, how the right to be paid (usually by monthly or stage/milestone payments) arises...
Read More >
9th Nov
Practice notes
Produced in association with 4 Pump CourtPrinciples of natural justiceIf an adjudicator breaches the rules of natural justice during the adjudication...
Read More >
9th Nov
Practice notes
The JCT Pre-Construction Services Agreement was launched in 2008. A revised edition was published in 2011 to incorporate the amendments to the Housing...
Read More >
9th Nov
Practice notes
This Practice Note examines the extent to which contractors, sub-contractors and consultants have a duty to warn their employer of inadequacies that...
Read More >
9th Nov
Practice notes
If a party is said to have ‘design liability’, it means that it bears legal responsibility for all or part of the design of a construction/engineering...
Read More >
9th Nov

Most recent Completion of the works content

Practice notes
What is the final account?The expression 'final account' refers to the consolidated financial summary which is presented by the contractor to the...
Read More >
18th Jan
Practice notes
It is common in construction projects for defects to manifest or appear in the works. Most construction contracts require the contractor to return to...
Read More >
18th Jan
Practice notes
The Limitation Act 1980 (LA 1980) (as amended by the Latent Damage Act 1986 (LDA 1986)) governs the time limits for bringing different types of legal...
Read More >
18th Jan
Practice notes
The nature of construction projects, the contracts agreed and the law surrounding them, means that claims are commonly made by one or more parties....
Read More >
18th Jan
Practice notes
Practical completion marks the end of the construction period of a project, when the works are 'finished' and the employer can occupy and/or use them....
Read More >
18th Jan
Practice notes
Taking occupation before practical completionThe default position in most building contracts is that the contractor is given exclusive possession of...
Read More >
18th Jan
Practice notes
What is sectional completion?Where the construction contract splits the works into sections or parts, usually to be started at different times, there...
Read More >
18th Jan
Practice notes
This Practice Note considers the Contractor’s obligations in relation to time under the JCT 2011 and 2016 contracts. It looks at commencement of work,...
Read More >
18th Jan
Practice notes
This Practice Note examines the concept of ‘time at large’ in relation to the completion of works under a construction contract, including what time...
Read More >
18th Jan
Practice notes
This Practice Note looks at the Contractor’s obligations in relation to commencement, progress and completion in the 2017 editions of the FIDIC...
Read More >
18th Jan
Practice notes
What is acceleration?Acceleration in construction law is generally understood to mean taking measures to speed up the works in order to complete them...
Read More >
18th Jan
Precedents
Date [insert date of Agreement]Parties1[insert name of Employer] of [insert address] incorporated in England and Wales with company registration...
Read More >
6th Dec
Q&As
Clause 2.29.2.1 of the JCT Design and Build Contract (DB) 2011/2016 provides that, where a Non-Completion Notice has been issued (due to the...
Read More >
6th Dec
Q&As
The general rule is that the limitation period will commence on the date on which the cause of action arises. A distinction is to be made between...
Read More >
6th Dec
Q&As
There is no single or universal definition of ‘snagging works’ (or the term ‘snagging list’ which is commonly used).The term ‘snagging’ is widely used...
Read More >
6th Dec
Q&As
As identified in Practice Note: Defects liability period and rectification of defects, there is no ‘standard’ definition of what constitutes a defect...
Read More >
6th Dec
Q&As
While we are aware of the occasional practice of a significant defect being carved out of a practical completion certificate (sometimes referred to as...
Read More >
6th Dec
Q&As
Retention is the name given to the amount of money the employer retains from interim payments as security for the future performance of the...
Read More >
6th Dec
Precedents
Snagging 1 The Architect/Contract Administra...
Read More >
26th Sep
Precedents
Defects (priority classification) ...
Read More >
26th Sep

Popular documents