The Secretary of State for the Department for Business, Energy and Industrial Strategy has refused development consent for the AQUIND Interconnector development project. The project was intended to be ‘for the construction, operation, maintenance and decommissioning of a linear 2,000 megawatt bi-directional subsea interconnector from the boundary of the EEZ in the English Channel to Lovedean in Hampshire, via a landfall at Eastney on Portsea Island, Portsmouth and a connection to an existing substation and associated infrastructure'.