Applying statutory requirements when drafting and negotiating construction contracts throws up common problems and disputes. We cover HGCRA 1996 requirements plus other issues lke retention, set off, and escrow.
In-depth guidance and precedent documents for enforcing and challenging the adjudicator’s decision. From correcting errors under the slip rule, to grounds for a jurisdictional challenge, this is the place to go.
We publish JCT 2016 contracts and FIDIC contracts, and have related schedules of amendments for key forms. See other schedules of amendments, practice notes, and checklists for forms including NEC, MF/1, ICC.
Understand the connection between the agreements you’re advising on and what happens on the ground. Know when to push a point or let it go, and give your clients advice they can work with from design to build and beyond.
Commercial analysis: The High Court has delivered a pivotal ruling recently in Jaevee Homes Ltd v Fincham (t/a Fincham Demolition) which confirms that...
The Office for National Statistics (ONS) has published data indicating a 1.2% increase in total construction output for Q2 2025. This was attributed...
This week's edition of Construction weekly highlights includes a guide to the Employer’s power to instruct under the Joint Contracts Tribunal (JCT)...
The Home Office and the Ministry of Housing, Communities and Local Government (MHCLG) have published a supplementary guidance on enforcing the...
Construction analysis: The government laid the draft Building Safety Levy (England) Regulations before parliament on 10 July 2025. The draft...
What is a variation on a construction project?A variation (sometimes referred to as a change) is an alteration to the scope of work originally...
EPC contracts—employer remediesEPC contracts are normally set up so that the contractor accepts much of the risk inherent in the project. The employer...
Cumulative impact claimsThis Practice Note provides an introduction to cumulative impact claims and considers how multiple variations instructed on a...
Good faith in commercial agreementsThis Practice Note considers good faith in commercial agreements. It examines the concept of good faith and the...
Building Safety Act 2022—landlord and tenant cases trackerThe Building Safety Act 2022 (BSA 2022) case tracker is a list of key landlord and...
Schedule of Amendments to SBCC Standard Building Contract With Quantities for use in Scotland (SBC/Q/Scot) 2016The Contract comprises the completed...
Modern Methods of Construction (MMC) and Net Zero Provisions for Construction or Development Agreements (Madhavi’s Clause) (The Chancery Lane...
Climate Aligned Construction Waste Management (Francis’ Clause) (The Chancery Lane Project)This Precedent green clause imports climate aligned waste...
Construction Materials: Procurement (Willow's Clause) (The Chancery Lane Project)This Precedent green clause sets a carbon budget for construction...
Schedule of Amendments to JCT Design and Build Contract 2024The Contract comprises the completed Design and Build Contract 2024 Edition published by...
What is a variation on a construction project?A variation (sometimes referred to as a change) is an alteration to the scope of work originally...
Time of the essence—construction contractsWhat does time of the essence mean?Where time is 'of the essence' it means that the stated time for...
Product liability insurance for the construction industryThis Practice Note looks at product liability insurance from the perspective of those engaged...
Escrow accounts and escrow agreementsThis Practice Note examines why parties involved in a construction project may enter into an escrow agreement (or...
Scott Schedules in construction disputesScott Schedules are often very useful in construction disputes. They help to identify the key issues between...
Differences between adjudication and other forms of dispute resolutionThis Practice Note identifies some of the key differences between adjudication...
Concession contracts—materials and resourcesA concession is a form of public private partnership (PPP). It is a long term contractual arrangement...
Professional indemnity insurance in construction projectsThis Practice Note looks at professional indemnity (PI) insurance in the context of...
Target cost contracts on construction projectsWhat is a target cost contract?A target cost contract is a type of cost reimbursable contract under...
Defects liability period and rectification of defectsIt is common in construction projects for defects to manifest or appear in the works. Most...
Retention of payment in construction contractsThe concept of a retention from interim payments is commonplace in commercial construction contracts,...
What is practical completion?Practical completion marks the end of the construction period of a project, when the works are 'finished' and the...
Quantum in construction claimsThis Practice Note looks at some of the key considerations that may need to be taken into account when a party to a...
Time at large in construction contractsThis Practice Note examines the concept of ‘time at large’ in relation to the completion of works under a...
Sub-contractors' insuranceThis Practice Note looks at how sub-contractors’ liability is typically covered by insurance and considers:•difficulties...
A term used to describe a way of structuring a property purchase to avoid paying VAT. The effect is to reduce the rate of VAT payable to 0%.
The process of removing tree stumps and roots from the ground, carried out as part of the preparation of the site for before construction commences.
In the JCT form of contract, an event which entitles the contractor to an extension of time in which to complete the works.