Applying statutory requirements when drafting and negotiating construction contracts throws up common problems and disputes. We cover HGCRA 1996 requirements plus other issues lke retention, set off, and escrow.
In-depth guidance and precedent documents for enforcing and challenging the adjudicator’s decision. From correcting errors under the slip rule, to grounds for a jurisdictional challenge, this is the place to go.
We publish JCT 2016 contracts and FIDIC contracts, and have related schedules of amendments for key forms. See other schedules of amendments, practice notes, and checklists for forms including NEC, MF/1, ICC.
Understand the connection between the agreements you’re advising on and what happens on the ground. Know when to push a point or let it go, and give your clients advice they can work with from design to build and beyond.
This week’s edition of Construction weekly highlights includes publication of the London Local Remediation Acceleration Plan to accelerate remediation...
Planning analysis: The government has published a consultation proposing to make changes to existing permitted development (PD) rights in England...
Construction analysis: The Technology and Construction Court (TCC) refused to grant summary judgment enforcing an adjudicator’s award of more than...
On 9 June 2026, Planning and Environment Decisions Wales (PEDW) published guidance called 'Using AI in submissions to PEDW', which sets out how...
Transport for London (TfL) has launched a consultation on proposals to extend the Docklands Light Railway (DLR) from Gallions Reach to Thamesmead via...
Purpose of environmental searches and investigationsEnvironmental investigations are carried out for several reasons. The cost, detail and scope of an...
Principles of natural justiceIf an adjudicator breaches the rules of natural justice during the adjudication then the decision may be a nullity if the...
What is design and build?At its simplest, design and build (D&B):•is a project delivery system under which a single entity (the D&B contractor)...
This Practice Note considers the test for an employer’s vicarious liability in tort, which arises from certain legal relationships and in relation to...
Administration is a procedure designed to give a company breathing space, with a view to either a rescue or a restructure or to allow for a better...
To [Insert Adjoining Owner]Of [Adjoining Owner’s main address][Insert Date]The Party Wall etc Act 1996Notice of proposed works—Line of Junction...
These Precedent green clauses are for insertion into construction contracts to adapt sustainable practices and net zero aligned provisions from the...
This Precedent green clause imports climate aligned waste management practices into traditional and design and build construction contracts. This...
This Precedent green clause sets a carbon budget for construction projects, along with the financial budget, to reduce greenhouse gas emissions. This...
1Interest on late paymentIf either party fails to make payment in accordance with this Agreement the other party shall be entitled, in addition to any...
What is a variation on a construction project?A variation (sometimes referred to as a change) is an alteration to the scope of work originally...
Time of the essence—construction contractsWhat does time of the essence mean?Where time is 'of the essence' it means that the stated time for...
Product liability insurance for the construction industryThis Practice Note looks at product liability insurance from the perspective of those engaged...
Escrow accounts and escrow agreementsThis Practice Note examines why parties involved in a construction project may enter into an escrow agreement (or...
Scott Schedules in construction disputesScott Schedules are often very useful in construction disputes. They help to identify the key issues between...
Differences between adjudication and other forms of dispute resolutionThis Practice Note identifies some of the key differences between adjudication...
Concession contracts—materials and resourcesA concession is a form of public private partnership (PPP). It is a long term contractual arrangement...
Professional indemnity insurance in construction projectsThis Practice Note looks at professional indemnity (PI) insurance in the context of...
Target cost contracts on construction projectsWhat is a target cost contract?A target cost contract is a type of cost reimbursable contract under...
Defects liability period and rectification of defectsIt is common in construction projects for defects to manifest or appear in the works. Most...
Retention of payment in construction contractsThe concept of a retention from interim payments is commonplace in commercial construction contracts,...
What is practical completion?Practical completion marks the end of the construction period of a project, when the works are 'finished' and the...
Quantum in construction claimsThis Practice Note looks at some of the key considerations that may need to be taken into account when a party to a...
Time at large in construction contractsThis Practice Note examines the concept of ‘time at large’ in relation to the completion of works under a...
Sub-contractors' insuranceThis Practice Note looks at how sub-contractors’ liability is typically covered by insurance and considers:•difficulties...
Government programme launched in 2004, for the rebuilding or refurbishment of every secondary school in England. The government announced the end of the BSF programme in 2010.
A professional, often engaged by a funder, to monitor the progress of construction works in order to protect its investment. Also known as a monitoring surveyor.
In construction, time bars commonly require a party (often the contractor) to comply with a notice provision within a specified period. If the provision is a condition precedent, the party may lose its entitlement (for example, to an extension of time) if it fails to meet the necessary deadline.