Applying statutory requirements when drafting and negotiating construction contracts throws up common problems and disputes. We cover HGCRA 1996 requirements plus other issues lke retention, set off, and escrow.
In-depth guidance and precedent documents for enforcing and challenging the adjudicator’s decision. From correcting errors under the slip rule, to grounds for a jurisdictional challenge, this is the place to go.
We publish JCT 2016 contracts and FIDIC contracts, and have related schedules of amendments for key forms. See other schedules of amendments, practice notes, and checklists for forms including NEC, MF/1, ICC.
Understand the connection between the agreements you’re advising on and what happens on the ground. Know when to push a point or let it go, and give your clients advice they can work with from design to build and beyond.
Construction analysis: The Building (Higher-Risk Buildings Procedures) (Wales) Regulations 2025, SI 2025 No 1321 (the Regulations) bring into force...
Arbitration analysis: In Lancor Holdings Ltd v Prem Kumar Menon, the Supreme Court of India held that while mere delay in rendering an arbitral award...
Mealey’s International Arbitration Report recently asked industry experts and leaders for their thoughts on the American Arbitration Association’s...
Practice Directions for the UK Supreme Court (UKSC) and the Judicial Committee of the Privy Council (JCPC) were amended on 22 December 2025. The...
The Ministry of Housing, Communities and Local Government (MHCLG) has published its third quarterly report on progress in implementing the Grenfell...
MoratoriumPart A1 of the Insolvency Act 1986 (IA 1986) provides for an process whereby directors of insolvent companies, or companies that are likely...
Exclusion and limitation of liabilityThis Practice Note considers exclusion and limitation of liability in business-to-business (B2B) contracts. It...
FIDIC contracts 2017—Contractor and Employer claimsIt is vital for parties to follow the correct procedure for making claims under the FIDIC...
Termination of a consultant's appointmentThis Practice Note looks at how consultant’s appointments might be terminated, explores the approach taken in...
CDM Regulations 2015—the health and safety fileUnder the Construction (Design and Management) Regulations 2015 (the ‘Regulations’), the health and...
Schedule of Amendments to JCT Intermediate Building Contract 2024Schedule of amendments to the jct intermediate building contract 2024The Contract...
Schedule of Amendments to JCT Intermediate Building Contract with contractor’s design 2024Schedule of amendments to the jct intermediate building...
Notice of assignment—construction projectsTo: [insert company name]Address: [insert address for the service of notices]Dear [insert name of...
Construction Pre-Action Protocol letter of claim—professional negligence claim against architect or engineerNote:•this Practice Note gives specific...
Construction Pre-Action Protocol letter of claim—defectsNote:•this Precedent gives specific guidance on matters proceeding in the Technology and...
What is a variation on a construction project?A variation (sometimes referred to as a change) is an alteration to the scope of work originally...
Time of the essence—construction contractsWhat does time of the essence mean?Where time is 'of the essence' it means that the stated time for...
Product liability insurance for the construction industryThis Practice Note looks at product liability insurance from the perspective of those engaged...
Escrow accounts and escrow agreementsThis Practice Note examines why parties involved in a construction project may enter into an escrow agreement (or...
Scott Schedules in construction disputesScott Schedules are often very useful in construction disputes. They help to identify the key issues between...
Differences between adjudication and other forms of dispute resolutionThis Practice Note identifies some of the key differences between adjudication...
Concession contracts—materials and resourcesA concession is a form of public private partnership (PPP). It is a long term contractual arrangement...
Professional indemnity insurance in construction projectsThis Practice Note looks at professional indemnity (PI) insurance in the context of...
Target cost contracts on construction projectsWhat is a target cost contract?A target cost contract is a type of cost reimbursable contract under...
Defects liability period and rectification of defectsIt is common in construction projects for defects to manifest or appear in the works. Most...
Retention of payment in construction contractsThe concept of a retention from interim payments is commonplace in commercial construction contracts,...
What is practical completion?Practical completion marks the end of the construction period of a project, when the works are 'finished' and the...
Quantum in construction claimsThis Practice Note looks at some of the key considerations that may need to be taken into account when a party to a...
Time at large in construction contractsThis Practice Note examines the concept of ‘time at large’ in relation to the completion of works under a...
Sub-contractors' insuranceThis Practice Note looks at how sub-contractors’ liability is typically covered by insurance and considers:•difficulties...
A site which has previously been developed for industrial or other urban uses.
See completion-completion-date'>Date for completion/completion date.
Construction of a building (usually offices) to include suspended ceilings and raised floors but no partitioning.