Construction analysis: The Technology and Construction Court enforced an adjudication decision, notwithstanding that the Notice of Adjudication had referred to the responding party by a trading name used by multiple companies at the same address, and that the claimant had (incorrectly) maintained during the adjudication that the defendant was not the contracting party.
To continue reading this news article, as well as thousands of others like it, sign in with LexisNexis or register for a free trial