The JCT Major Project Construction Contract 2024—what’s changed?

Published on: 18 October 2024

Table of contents

  • What are the Major Project contracts used for?
  • MPCC 2024—what’s changed?
  • Extensions of time (clause 18)
  • Standards of design, materials and workmanship (clause 11)
  • Payment (clause 28)
  • Termination (clauses 39–41)
  • Building regulations and building safety
  • Other changes to note
  • MP/Sub 2024—what’s changed?

Article summary

Construction analysis: On 16 October 2024, the Joint Contracts Tribunal (JCT) published the 2024 editions of its Major Project, Constructing Excellence, and Prime Cost Building contracts, along with their associated guides and sub-contracts. In this analysis, we focus on the Major Projects contract and sub-contract, and look at how these differ from their 2016 equivalents.