Legal News

Specific and pre-action disclosure allowed in procurement dispute (Roche v Mid Yorks Hospitals NHS Trust)

Published on: 24 April 2013

Table of contents

  • Practical implications
  • Court details
  • Facts
  • Judgment
  • Specific disclosure
  • Pre-action disclosure
  • Costs

Article summary

The TCC has ordered specific disclosure under CPR 31.12 and pre-action disclosure under CPR 31.16 of certain categories of documents. In doing so, it has given guidance on the principles of early and pre-action disclosure in procurement disputes (considering Mears and Sumitomo). It also made a reduction in the costs awarded to reflect the over-extensive nature of the claimant’s application.