Ofwat has published guidance establishing the midpoint review process for the Major Water Infrastructure Programme (MWIP), which encompasses 30 large-scale water infrastructure projects identified in the 2024 price review (PR24). The guidance creates a combined gated process integrating The Regulators Alliance for Progressing Infrastructure Development (RAPID) oversight of early project development with Ofwat's Major Projects team regulation of later stage delivery. The midpoint review occurs between gate A and gate B during the Initial Development stage and replaces the previous Strategic regional water resource solutions guidance for gate two. While not constituting a formal gate or funding decision point, the review provides structured regulatory feedback to project owners. The guidance sets out detailed submission requirements across 12 assessment areas including needs case, project design, water resources, costs and benefits, programme management, land and planning, environmental considerations, drinking water quality, procurement, risks, board assurance and stakeholder engagement. Project owners must submit approximately 40–50 page reports, with RAPID providing feedback within 10 weeks and categorising any concerns as priority actions, actions or recommendations to ensure projects remain on track for gate B submissions.