Construction analysis: The Technology and Construction Court considered the interaction between bespoke and standard form contractual provisions, in a contract based on a Joint Contracts Tribunal (JCT) Design and Build Contract 2016. The contractor sought several declarations relating to the scope of its responsibilities under the contract, and the limits of an adjudicator’s power to fix the completion date for the works. The TCC found that, among other things, a schedule of derogations qualified the contractor’s design responsibility, pending certain conditions being met. However, it declined to grant a declaration relating to the allocation of planning risk under the contract, concluding that this was not a matter that could be decided without a fact-specific application. The TCC further confirmed that adjudicators have power under the Scheme for Construction Contracts to review and revise extensions of time, including by fixing an earlier completion date than one established through the contractual extension of time process.