Keating Chambers

Experts

7

Filter by: Practice area
Abdul Jinadu
Barrister
Keating Chambers
Adam Constable
Keating Chambers
Brenna Conroy
Barrister, Keating Chambers
Keating Chambers
Calum Lamont
Keating Chambers
Philip Boulding
Keating Chambers
Rhodri Williams
Barrister
Keating Chambers
Simon Hughes
Keating Chambers
Contributions by Keating Chambers Experts

19

Introduction to public procurement in Wales—PA 2023
Introduction to public procurement in Wales—PA 2023
Practice Notes

This Practice Note provides an introduction to public procurement in Wales under the Procurement Act 2023 (PA 2023) and the Procurement (Wales) Regulations 2024, highlighting in particular the differences in the public procurement rules in Wales, as compared with England. It also provides an overview of the rules applicable to healthcare procurement in Wales, as well as duties imposed under the Social Partnership and Public Procurement (Wales) Act 2023.

Key considerations at the pre-action stage of a construction dispute
Key considerations at the pre-action stage of a construction dispute
Practice Notes

This Practice Note sets out the steps which should be taken at the pre-action stage of a construction dispute and the key considerations. This includes initial information to be gathered and reviewed, preliminary advice to be considered, strategic considerations, witnesses and experts, considering settlement, interim relief and advising on costs.

An employer has served a default notice to terminate a JCT Design & Build 2011 contract on the basis of
An employer has served a default notice to terminate a JCT Design & Build 2011 contract on the basis of
Q&A

This Q&A considers whether an employer who has already served a notice to terminate a JCT D&B 2011 contract on the basis of a specified default by the contractor can use a new issue/ground for termination that subsequently arises in its argument for termination.

Are you aware of any cases or guidance regarding an independent design checker’s liability when it
Are you aware of any cases or guidance regarding an independent design checker’s liability when it
Q&A

This Q&A considers the liability of a consultant appointed by the employer to review and approve a design developed by a contractor in a design and build contract. This role is sometimes known as an independent checker/reviewer or simply the employer’s design consultant (in a traditional procurement situation, this latter term could also describe a designer engaged by the employer to undertake design work).

Can a party correct mistakes in a pay less notice in response to a final account claim?
Can a party correct mistakes in a pay less notice in response to a final account claim?
Q&A

This Q&A looks at whether a party (payee or paying party) can correct mistakes in a pay less notice that was given in response to a default payment notice for a final account. It focuses on the position under the JCT forms of contract and similar contracts which contain provisions for the final account to become final and conclusive after a defined period.

Can a party to a construction contract unilaterally decide to bring court proceedings without first
Can a party to a construction contract unilaterally decide to bring court proceedings without first
Q&A

This Q&A considers the right of a party to a construction contract to commence court proceedings without first having referred the dispute to adjudication.

Can an employer rescind an extension of time it has previously given? What if the contractor has relied
Can an employer rescind an extension of time it has previously given? What if the contractor has relied
Q&A

This Q&A considers whether an employer has the power to rescind the award of an extension of time and what happens if the contractor has relied on the extension of time granted.

Does the HGCRA 1996 apply to operation and maintenance contracts in respect of power-generating
Does the HGCRA 1996 apply to operation and maintenance contracts in respect of power-generating
Q&A

This Q&A considers whether the Housing Grants, Construction and Regeneration Act 1996 applies to operation and maintenance (O&M) contracts in respect of power-generating facilities.

How does the disclosure pilot scheme (DPS) under CPR PD 51U impact on proceedings in the Technology and
How does the disclosure pilot scheme (DPS) under CPR PD 51U impact on proceedings in the Technology and
Q&A

This Q&A considers how the disclosure pilot scheme will be applied in the Technology and Construction Court (TCC), particularly in respect of potential conflicts between the pilot scheme and TCC practice, such as the timing of the case management conference and the use of the TCC eDisclosure Protocol.

If a construction project is under a JCT Intermediate Building Contract with Contractor’s Design 2016, is
If a construction project is under a JCT Intermediate Building Contract with Contractor’s Design 2016, is
Q&A

This Q&A considers the impact of the contractor’s insolvency on retention monies held by the employer under a JCT Intermediate Building Contract with Contractor's Design 2016.

If an employer asks a contractor to build something that will not comply with the Building Regulations,
If an employer asks a contractor to build something that will not comply with the Building Regulations,
Q&A

This Q&A considers whether there is a duty imposed on a contractor to inform the employer that the build does not comply with the Building Regulations 2010, SI 2010/2214.

Is a contractor entitled to an extension of time if construction works are delayed due to the impact of
Is a contractor entitled to an extension of time if construction works are delayed due to the impact of
Q&A

This Q&A considers whether a contractor is entitled to an extension of time if works are delayed as a result of coronavirus (COVID-19).

Is there any guidance on whether a pay less notice can specify a negative sum?
Is there any guidance on whether a pay less notice can specify a negative sum?
Q&A

This Q&A considers whether a paying party can specify a negative sum in a pay less notice, considering guidance from relevant statutory and case law sources.

What amendments to the JCT Design and Build Contract 2011 should be included where the employer is taking
What amendments to the JCT Design and Build Contract 2011 should be included where the employer is taking
Q&A

This Q&A considers what amendments, if any, need to be made to JCT Design & Build 2011 where an employer is taking out non-negligent insurance under clause 6.5.1 instead of the contractor.

What effect do the errata to the FIDIC 2017 contracts have on contracts that have already been entered
What effect do the errata to the FIDIC 2017 contracts have on contracts that have already been entered
Q&A

This Q&A considers the effect of the errata to the FIDIC Red, Yellow and Silver Books 2017 on contracts which have already been entered into.

What is the difference between termination, determination and a voided contract?
What is the difference between termination, determination and a voided contract?
Q&A

This Q&A looks at what the differences are, if any, between a void contract, terminating a contract and determining a contract.

When claiming interest in an adjudication, when does it run from, eg the date of the breach, the start of
When claiming interest in an adjudication, when does it run from, eg the date of the breach, the start of
Q&A

This Q&A considers when an adjudicator can award interest in an adjudication, and the time from which interest accrues. The date on which interest starts to run will vary depending upon the basis on which interest is awarded.

Where a builder working on property A causes damage to a neighbouring property, who is liable to the
Where a builder working on property A causes damage to a neighbouring property, who is liable to the
Q&A

This Q&A considers where potential claims and areas of liability that may arise when a builder causes damage to a neighbouring property.

Would a clause in a sub-contract fall foul of HGCRA 1996, s 113 if it provided for the sub-contractor to
Would a clause in a sub-contract fall foul of HGCRA 1996, s 113 if it provided for the sub-contractor to
Q&A

This Q&A considers whether a clause providing for a sub-contractor to be paid by the earlier of (i) the date when the contractor is paid and (ii) a long-stop date would fall foul of the prohibition on ‘pay when paid’ clauses under section 113 of the Housing Grants, Construction and Regeneration Act 1996.

If you expected to see yourself on this page, click here.