Construction Pre-Action Protocol letter of claim—variation dispute
Construction Pre-Action Protocol letter of claim—variation dispute

The following Construction precedent provides comprehensive and up to date legal information covering:

  • Construction Pre-Action Protocol letter of claim—variation dispute

[ON THE HEADED NOTEPAPER OF CLAIMANT’S SOLICITORS]

[Name of defendant or defendant’s solicitor, if known]

[Address]

[Date]

Dear [insert contact name]

[Insert names of parties and project, and any relevant references—for example:]

De Ziner House: Superman Contractors Ltd v Joe Bloggs

Your reference: BLO001.1

Our reference: SUPER232

    1. 1

      [As you are aware, we OR We] act for Superman Contractors Ltd (‘Superman’)[ in respect of its claim against your client, Joe Bloggs, regarding payment for the additional sun room constructed at De Ziner House]. [We refer to our previous correspondence, in particular our letter of [date], relating to this matter, to which we have had no[ satisfactory] response.]

    1. 2

      This letter of claim is written in accordance with the Pre-Action Protocol for Construction and Engineering Disputes (the ‘Protocol’), a copy of which is enclosed for your ease of reference. Ignoring this letter and failing to comply with the Protocol may increase your client’s liability for costs.

    1. 3

      Pursuant to section 8 of the Protocol, you are required to acknowledge receipt of this letter of claim by [insert date 14 days from receipt], and to provide your substantive response by [insert date 28 days from receipt]. In the absence of an acknowledgement or substantive response to this letter within the timescales we have set out, our client is entitled to commence proceedings without further reference to your client, and your client’s conduct will be brought to