No green light for recovery of traffic management costs under service contract (Dynniq v Lancashire)

No green light for recovery of traffic management costs under service contract (Dynniq v Lancashire)
Published on: 11 December 2017
Published by: LexisPSL
  • No green light for recovery of traffic management costs under service contract (Dynniq v Lancashire)
  • Original news
  • What are the practical implications of this case?
  • What was the background?
  • What did the court decide?
  • Contrary to other provisions?
  • Surplusage?
  • Case details

Article summary

Construction analysis: The court held that the costs of traffic safety and management were already included in the prices for items set out in the Price List under an NEC3 Term Service Contract. Accordingly, the contractor was not entitled to additional payment in respect of such services. or take a trial to read the full analysis.