Article summary

Construction analysis: The Northern Irish court considered the approach to assessing a compensation event under an NEC3 Professional Services Contract. It held that, as the additional work had been completed at the time of the assessment, the assessment was to be carried out by reference to the actual costs incurred. This was even though the contract contemplated the assessment being carried out at an earlier stage by reference to forecast costs. or take a trial to read the full analysis.