[100A Wales: consultation etc in respect of certain applications relating to planning permission]
[100A Wales: consultation etc in respect of certain applications relating to planning permission]

[(1)     A development order may provide that a local planning authority in Wales to which an application within subsection (5) (a “relevant application”) is made are not to determine the application before the end of a period specified in the order.

(2)     If a local planning authority in Wales to which a relevant application is made consult a statutory consultee about the application, the consultee must give a substantive response.

(3)     That response must be given before the end of—

(a)     a period specified in a development order, or

(b)     if the consultee and the authority agree otherwise in writing, whatever period is specified in their agreement.