95 Effect of completion notice
95 Effect of completion notice

(1)     A completion notice shall not take effect unless and until it is confirmed by the Secretary of State.

(2)     In confirming a completion notice the Secretary of State may substitute some longer period for that specified in the notice as the period at the expiration of which the planning permission is to cease to have effect.

(3)     If, within such period as may be specified in a completion notice (which must not be less than 28 days from its service) any person on whom the notice is served so requires, the Secretary of State, before confirming the notice, shall

63 . . .
64 . . .
66 . . .
67 . . .
68 . . .
76 . . .
80 . . .
81 . . .
105 . . .