[261R Procedure when refusing approval of a proposal under section 261Q]
[261R Procedure when refusing approval of a proposal under section 261Q]

[(1)     If the FCA proposes to refuse approval of a proposal under section 261Q to replace the depositary or operator of an authorised contractual scheme, it must give a warning notice to the person by whom notice of the proposal was given under section 261Q(4) or (5).

(2)     If the FCA proposes to refuse approval of a proposal under section 261Q to alter an authorised contractual scheme, it must give separate warning notices to the operator and the depositary of the scheme.

(3)     To be valid the warning notice must be received by the person to whom it is given before the end of one month beginning with the date on which notice of the proposal was given.

. . .
270 . . .