How are the costs of budget drafting (1% of approved budget or £1,000) and budget process (2%) in a budgeted case recovered? Should they be added into the bill of costs or is there a different process?

read titleRead full title
Published on LexisPSL on 21/05/2019

The following Dispute Resolution Q&A provides comprehensive and up to date legal information covering:

  • How are the costs of budget drafting (1% of approved budget or £1,000) and budget process (2%) in a budgeted case recovered? Should they be added into the bill of costs or is there a different process?

How are the costs of budget drafting (1% of approved budget or £1,000) and budget process (2%) in a budgeted case recovered? Should they be added into the bill of costs or is there a different process?

See the model electronic bill of costs, Precedent S and specifically sheet 15, entitled ‘ReferenceTable—Phase