620. Plans of work and notification of work with asbestos.

An employer1 must not undertake any work with asbestos2 unless he has prepared a suitable written plan of work (the 'plan of work') detailing how that work is to be carried out3. The employer must keep a copy of the plan of work at those premises at which the work to which the plan relates is being carried out for such time as that work continues4. In cases of final demolition or major refurbishment of premises, the plan of work must, so far as is reasonably practicable5, specify that asbestos is to be removed before any other major works begin, unless it would cause a greater risk to employees than if th