358. Payment provisions under the scheme for construction contracts.

Where a construction contract1 does not comply with the requirements of the payment provisions under the Housing Grants, Construction and Regeneration Act 1996, 2the relevant provisions of the scheme have effect3.

Where the parties to a relevant construction contract4 fail to agree: (1) the amount of any instalment or stage or periodic payment for any work under the contract5; or (2) the intervals at which, or circumstances in which, such payments become due under that contract6; or (3) both the amount of any instalment or stage or periodic payment and the intervals at which or circumstances in which such payments become due7, then the relevant