221. Failure to finalise contract and estoppel.

If a contractor carries out work in circumstances in which no contract has been concluded, he may, but will not necessarily, be entitled to remuneration on a quantum meruit basis1. The rates or basis of remuneration that would have been included in the contract had it been concluded will be taken into account in determining that reasonable remuneration